Interstate 10 Construction Update

Friday, May 3rd, 2019 From Mayor Kalkomey

Here is a brief summary of what we should expect to see on IH10 in the next 12-18 months.

1. The frontage roads will convert to one-way next week between the river and Koy Road. We will have to exit where we normally do westbound and U-turn at Mlcak. They will
reduce the frontage roads to one lane while constructing 2 new lanes. Then they will switch traffic to new frontage road lanes and rebuilt the remaining lane. Then they will place a concrete barrier between the two outer frontage road lanes and divert all IH10 to the inner two frontage road lanes. This will allow them to fully rebuild the main lanes. It probably takes a year to rebuild the frontage roads before they start to divert the main lanes.
2. The FM 1458 (San Felipe exit) overpass and Mlcak Road overpass will be removed and rebuilt. They think FM1458 will be first, which may give them time to build some of the Chew Road interchange to give us some relief westbound. If not, then our U-turn will be FM1458 instead of Mlcak.
3. They will do the westbound river bridge first. Materials for new bridge scheduled for August. So westbound traffic will be diverted to the eastbound bridge. They say the bridge can accommodate 4 lanes of traffic. I suspect it will be tight. Schedule has to coordinated with the work on the Waller County side, so schedule may change.
4. We discussed the issues with all of the accidents on the Waller County side of the river and how those are impacted by the construction methods. This TxDOT office is well aware of the situation, and will make all practical efforts to not duplicate those conditions.
5. This contractor was not the low bidder. The same one on the Waller side was low. But the second low bidder bid a shorter time. So TxDOT chose the shorter schedule. But that schedule is still 3 1/2 years, with incentives to reduce that to 3 years. So even with that we are still looking at early 2022 for completion.
6. Be patient.